Improving well cementing efficiency in complex mining and geological conditions through the use of a sub-preventer sealer
https://doi.org/10.21285/2686-9993-2026-49-1-7
EDN: RXHRBC
Abstract
The purpose of this work is to improve the safety and cost-effectiveness of the counter-cementing process of casing strings under conditions of lost circulation and the risk of gas, oil, and water shows, using the Yurubcheno-Tokhomskoye field as an example. The causes of frequent failures of the universal preventer during the counter-cementing with the closed universal preventer in order to create a vacuum effect were analysed. The study was given to the geological and technical conditions of the Yurubcheno-Tokhomskoye field, which led to 28 cases of equipment failure in 2023–2024. The design and operation principle of the sub-preventer sealer as an alternative technological solution were considered. A comparative technical and economic assessment of the sealer implementation was performed and the discounted cash flow, payback period, and profitability index were calculated. It was determined that the main cause of universal preventer failures was due to the operation of the sealing element in an aggressive cement slurry environment under the influence of a vacuum. It led to the loss of the second safety barrier. The proposed solution (to install a sub-preventer sealer between the casing head flange and the blowout preventer crosspiece) allows to seal the annular space of the casing string without the use of a universal preventer. The feasibility study showed that a one-time investment of 16 million rubles for equipping 5 drilling rigs covers the expenses during the first year of operation providing significant annual savings by eliminating the repair cost of the drilling rigs. The introduction of a sub-preventer sealer makes it possible to eliminate a major technological risk of second barrier failure during counter-cementing, thereby increasing the industrial safety of work. The technical solution is economically feasible since its yield index is <1 and its discounted payback period is less than a year. It can be recommended for use in fields with similar complex mining and geological conditions.
About the Authors
V. O. SobennikovRussian Federation
Valentin O. Sobennikov, Postgraduate Student, Institute of Subsoil Use
Irkutsk
Competing Interests:
The authors declare no conflict of interests.
E. N. Gura
Russian Federation
Eduard N. Gura, Technical Director
Zhukov
Competing Interests:
The authors declare no conflict of interests.
S. A. Sverkunov
Russian Federation
Sergey A. Sverkunov, Cand. Sci. (Eng.), Associate Professor of the Department of Oil and Gas Production, Institute of Subsoil Use
Irkutsk
Competing Interests:
The authors declare no conflict of interests.
A. G. Vakhromeev
Russian Federation
Andrey G. Vakhromeev, Dr. Sci. (Geol. & Mineral.), Professor of the Department of Oil and Gas Engineering, Institute of Subsoil Use; Head of the Laboratory of Oil, Gas and Hydromineral Raw Materials; Expert of the Technological Development Department of the Numerical and Mathematical Modeling Group
Irkutsk; Krasnoyarsk
Competing Interests:
The authors declare no conflict of interests.
A. N. Buglov
Russian Federation
Artem N. Buglov, Master’s Degree Student, Institute of Subsoil Use
Irkutsk
Competing Interests:
The authors declare no conflict of interests.
D. D. Gladyshev
Russian Federation
Danila D. Gladyshev, Master’s Degree Student, Institute of Economics,Management and Law
Irkutsk
Competing Interests:
The authors declare no conflict of interests.
References
1. Foroushan H.K., Lund B., Ytrehus Ja.D., Saasen A. Cement placement: an overview of fluid displacement techniques and modelling. Energies. 2021;14(3):573. https://doi.org/10.3390/en14030573. EDN: RAKHTJ.
2. Mahmoud A.A., Abdelaal A., Adjei S., Elkatatny S. Foamed cement applications in oil industry based on field experience: a comprehensive review. ACS Omega. 2024;9:9. https://doi.org/10.1021/acsomega.3c07580.
3. Sayindla S., Lund B., Ytrehus J.D., Saasen A. Hole-cleaning performance comparison of oil-based and water-based drilling fluids. Journal of Petroleum Science and Engineering. 2021;159:49-57. https://doi.org/10.1016/j.petrol.2017.08.069.
4. Veliyev E.F., Aliyev A.A. Comparative analysis of the geopolymer and Portland cement application as plugging material under conditions of incomplete displacement of drilling mud from the annulus. SOCAR Proceedings. 2022;1:108-115. https://doi.org/10.5510/OGP20220100637.
5. Wang H., Huang H., Bi W., Ji G., Zhou B., Zhuo L. Deep and ultra-deep oil and gas well drilling technologies: рrogress and prospect. Natural Gas Industry. 2022;9(2):141-157. https://doi.org/10.1016/j.ngib.2021.08.019. EDN: UCQWGJ.
6. Bykov V.V., Paleev S.A., Akhmetzyanov R.R., Zaharenkov A.V., Zakirov N.N. An integrated approach to cementing casing strings in difficult conditions of fields in Eastern Siberia. Oil Industry. 2024;8:58-61. (In Russ.). https://doi.org/10.24887/0028-2448-2024-8-58-61. EDN: HUKHNA.
7. Darvish S. Achieving zonal isolation in the second largest oil field in the world: decade of training (Rumaila field, Iraq). In: SPE/IADC Drilling Conference. OnePetro. 2025.
8. Diachenko O.I. The method of oil and gas fields operational efficiency management. Scientific Journal Economic Sciences. 2016;12:76-82. (In Russ.). EDN: YJBHUD.
9. Zalivin V.G. Resource-saving technologies of foam application in wells drilling. Onshore and offshore oil and gas well construction. 2025;8:43-49. (In Russ.). EDN: IPASCM.
10. Ismagilova E.R. Development the self-healing concept for well cement support integrity maintenance. theory and practice. Kazakhstan Journal for Oil and Gas Industry. 2024;6(1):64-73. https://doi.org/10.54859/kjogi108662. EDN: TZVZRC.
11. Kryuchkov D.O., Pivovar A.V., Kuznetsova L.S., Kizimov P.L. Real time seismogeological analysis while drilling is the first step to oilfield development efficiency. Oilfield engineering. 2024;4:34-42. (In Russ.). EDN: WAFYYG.
12. Legostaev A.M., Khairullin B.Y., Vityazev O.L. Rotary mouth sealer. Patent RF, no. 2684261; 2019. (In Russ.).
13. Nersesov S.V., Mosienko V.G., Gasumov R.A., Chernukhin V.I., Ostap O.S., Minlikaev V.Z., Klimanov A.V. Method of stepwise drilling of a well under conditions of abnormally low reservoir pressures in the absorption zone. Patent RF, no. 2188302; 2002. (In Russ.).
14. Pivovar A.V., Kolesov V.A., Kalistratov S.A., Zagrivniy F.A., Mishakov M.V. Influence of geological conditions on wear-out of the bits in the Riphean deposits of the Yurubcheno-Tokhomskoye field. Oil Industry. 2022;1:50-53. (In Russ.). https://doi.org/10.24887/0028-2448-2022-1-50-53. EDN: VLAOSB.
15. Pivovar A.V., Pleshko N.N., Filatova V.P., Kryuchkov D.O. Optimization of horizontal well drilling in carbonate reservoirs of eastern Siberia: results from the application of seismic-geological analysis. Oil Industry. 2025;5:94-98. (In Russ.). https://doi.org/10.24887/0028-2448-2025-5-94-98. EDN: NBSTYG.
16. Ryzhenko V.Iu. Russian oil industry: state and problems. Perspectives of Science and Education. 2014;1:300-308. (In Russ.). EDN: RVOKMP.
17. Samsonenko N.V., Mnatsakanov V.A., Mansurov M.N., Potapov A.G. Problems of primary cementing of horizontal gas production wells at the Kharasaveyskoe gas-condensate field. Onshore and offshore oil and gas well construction. 2026;1:37-43. (In Russ.). EDN: URCINR.
18. Chernyshov S.E., Ashikhmin S.G., Kashnikov Yu.A., Savich A.D., Mosin A.V., Chulrhlov A.S. Evaluation of the cement sheath safety after shaped charge perforation considering the criterion of cement stone destruction. Oil Industry. 2021;6:50-53. (In Russ.). https://doi.org/10.24887/0028-2448-2021-6-50-53. EDN: QNHGRQ.
19. Shamilov V.M., Abdullayev A.I., Guliyev I.B., Safarov Yа.O., Shamilov F.V. The influence of nanostructured cement slurry on the quality of well cementing. Oil Industry. 2025;3:52-55. (In Russ.). https://doi.org/10.24887/0028-2448-2025-3-52-55. EDN: GHJSVQ.
20. Shut K.F., Khrabrov V.A. Study of hollow microspheres stability to the alkaline environment of cement slurry. Construction of oil and gas wells on land and sea. 2026;2:39-43. EDN: JXIIJR.
Review
For citations:
Sobennikov V.O., Gura E.N., Sverkunov S.A., Vakhromeev A.G., Buglov A.N., Gladyshev D.D. Improving well cementing efficiency in complex mining and geological conditions through the use of a sub-preventer sealer. Earth sciences and subsoil use. 2026;49(1):84-95. https://doi.org/10.21285/2686-9993-2026-49-1-7. EDN: RXHRBC
JATS XML





















